Extension of line 11 of the Paris Metro

Publié le 30 January 2020

As part of a consortium, ETF is extending Line 11 eastwards for its client RATP from Mairie des Lilas station to Rosny-Bois-Perrier.

Signed in December 2017, construction began in 2019 and will last for four years. This extension includes the creation of six new stations over 6.5 km and a maintenance workshop.

The project is divided into two phases:

  • Phase 1: The Rosny loop: May 2019 – September 2020
  • Phase 2: Tunnel connection between Rosny and Mairie des Lilas: from spring 2021 to 2022.

The new platform will consist of

  • 12.6 km of track
  • 25.2 km of rails, running tracks and guide bars
  • 12 points (4 in line and 8 in AMT)

In order to adapt to the specific characteristics of the environment, several types of track will be constructed: concrete track, ballast track, etc. Up to 100 employees will be mobilised at the peak of activity.