Kick-off of rail works for the future T10 tramway line

Publié le 11 December 2020

One year after the start of urban development work, the T10 tramway project has reached a milestone with the laying of the first rails at the end of November 2020. This autumn, these first rails and sleepers were transported by exceptional convoys to the site of the future maintenance and storage workshop for the line. In total, more than 1,600 18-meter long rails and 40,000 sleepers will be used to connect Antony to Clamart.

This project which should last until the end of 2022 is being carried out by ETF for the track/catenary section and by Eurovia for the civil engineering section.