The Suite Rapide Zone Dense finished its 2020 campaign with 100% of the trackage completed

Publié le 14 December 2020

In the night of 10 to 11 December 2020, TEVO completed its 2020 campaign with 100% of its trackage completed:
– 80,4 km of track renewed
– an average daily output of over 400 m/day
– 95 % of equipment availability

A great team effort in synergy with our partners involved in the Zone Dense project! From the rear base to the finishing work, it is thanks to the mobilisation and commitment of the operational staff that this very special year is a success.